The sane lobby on the impossibilist policies on Nuclear Power are talking sense to power. No-one is listening.
• Jonathon Porritt, Tom Burke, Charles Secrett and Tony Juniper have produced a series of six briefings to help inform the public debate about nuclear power. On 12 March, they wrote to the prime ministerto warn him that his current proposals will end in failure. As yet, they have not received a reply.
Nuclear policy: part of the Government’s omnishambles
Posted on April 30, 2012 by tomburke
The collapse of the Government’s nuclear policy is a somewhat overlooked part of its current omnishambles. In part this is because very few of the journalists writing about nuclear power know much about the subject. Most continue to assert that all but one of Britain’s current nuclear power stations will be shut in this decade even though it is three months since EDF announced that it was seeking life extension for its existing fleet.
This means that some of our current AGRs may still be working in 2030. After all, if you were EDF why wouldn’t you want to take advantage of the massive windfall created by the carbon support price for an extra ten years? Much cheaper and less risky than building new reactors.
Meanwhile the Government from the Prime Minister down is talking to anyone who will listen about buying Horizon, the nuclear consortium which EoN and RWE have just withdrawn from. Even if you thought that it was a good idea to hand over control of your energy policy to Russian gangsters or the Chinese government, the really big problem with nuclear remains unsolved.
Horizon is a joint venture set up by the two German utilities. It has no assets. In order to borrow the £30 billion or so that would be needed to pay for the reactors someone with very deep pockets is going to have to guarantee the loans. It won’t be the British Government.
Whoever it might be would be taking a big bet that a company with no track record in building nuclear power stations would be able to do so on time and to budget – something Areva with all its experience has so far found impossible. They would also be taking a very big bet that the Treasury will be willing to allow a 30 year lock-in to nuclear electricity costs that are on a par with off-shore wind.
The eye-watering expense of nuclear power
The coalition wants us to depend more and more on nuclear power, but quite simply, it is too expensive to be able to deliver
Sizewell nuclear power plant, seen from across the sea at Southwold, Suffolk. Photograph: Graham Turner for the Guardian
Just for a moment, forget whether you're pro-nuclear or anti-nuclear, and reflect on the coalition government's policy for nuclear power.
It wants to see 10 new reactors built over the next few years. It sees this as a critical part of its carbon management strategy, and absolutely necessary to help "keep the lights on". It believes it will strengthen the UK's energy security at a time when North Sea oil and gas continues to decline. It is working closely with a wide range of energy companies to help deliver the 10 new reactors. That's the plan. Some think it's great; some don't much like it, but see it as a necessary part of addressing accelerating climate change; some think it is seriously misguided.
It doesn't really matter what you think: it cannot possibly deliver – primarily for economic reasons.
Nuclear reactors are massively expensive. They take a long time to build. And even when they're up and running, they're nothing like as reliable as the industry would have us believe. Few if any companies have balance sheets that are strong enough to cover the capital costs of a new reactor – with a starting price today of about £6bn, and growing by an average of 15% per annum. For that reason, the funding has to come either from private investors or from governments: no reactor has ever been built anywhere in the world without substantial government subsidy, and no reactor ever will be built without substantial government funding in future.
However, private investors are not enamoured by nuclear power. The construction risks are too high (with cost overruns and substantial delays all but guaranteed), and the political risks (with governments constantly changing their mind about levels of support) even higher. The higher the risk, the higher the costs of capital.
Which means governments always have to step in – including the UK government. For the time being, ministers in DECC are sticking to the wording of the Coalition Agreement that a new nuclear programme can only proceed "provided that they receive no public subsidy". This is now so transparently dishonest that it will not be possible to maintain that fiction for much longer, especially when the details of the electricity market reform (EMR) proposals are published.
Here's their dilemma. Ministers wanted to have lots of companies competing to build the ten reactors. Three of the most significant players, (RWEnpower, EON UK and Scottish and Southern Electricity), have already dropped out. Both GDFSuez and Centrica have been giving out very strong signals to investors that they are about to drop out. Most of the rest of the companies left in are too small or incapable to bother about. That leaves EDF, a nuclear giant, 85% owned by the French government.
Just three years ago, EDF's chief executive could be heard crowing about the fact that EDF would need no public subsidy to build its EPRs (European pressurised reactors) here in the UK. Today, his senior directors are pretty much permanently camped out in the Department of Energy and Climate Change (DECC) demanding eye-watering levels of financial support for the four reactors they hope to build at Hinkley Point and Sizewell.
The going wholesale price for electricity at the moment is around £45/MWh. Under the EMR, the government is offering "contracts for difference" to cover the extra cost of nuclear – the so-called "strike price". Calculating the scale of those extra costs is tricky, not least because it is impossible to believe anything the industry says about future costs. Estimates vary between £60/MWh and £90/MWh, with most independent commentators veering towards the high end rather than the low end.
The amount of subsidy required for just four reactors, £90/MWh, would be £2bn a year for 30 years. £60bn. For 10 reactors, it would be £5bn a year for 30 years. £150bn
And you need to understand that this figure doesn't take into account any of the other forms of subsidy on offer (be it in the form of a carbon price floor or massively subsidised insurance arrangements to cover the possibility of nuclear accidents), let alone the massive liabilities for cleaning up our existing nuclear power programme, which come in at about £7bn a year.
From a taxpayers' point of view, that's a minimum of £12bn a year to support an industry that is meant to be receiving "no public subsidy". The implications of all this for an already shambolic government are enormous. George Osborne is deeply concerned about the costs of "the green agenda". How could he possibly wave this through in the name of a low-carbon economy, when he could get infinitely better value for our money by investing in energy efficiency and renewables?
And as for the Lib Dems, either they renege on the Coalition Agreement, and come out firmly against these proposals, or they go into the next election as liars to a man and woman.
If, as the Coalition maintains, it's wrong to pass the burden of debt on to our children and granchildren, how can it be right to gift them a toxic legacy of nuclear waste to clear up?
Posted by: DG | May 09, 2012 at 01:45 PM
Or allow Russian crooks or Chinese billionaires to feat off new nuclear subsdies now Japan has proved the fragility of nuclear power.
Posted by: Paul Flynn | May 07, 2012 at 09:56 PM
Dear Paul,
Please raise the question of why EDF should require a £60 billion subsidy for four nuclear reactors that should cost only (only!) £20 billion to build at the next Energy Questions.
Why should British consumers give a vast windfall to the French treasury in return for a relatively small amount of power generation but a great deal of nuclear waste?
Posted by: Tony Roberts | May 06, 2012 at 06:09 PM